Pittwater Council – GPT Repair and Upgrades

Further to the audit of their 51 GPTs, Optimal Stormwater was selected to do minor capital works on several of the GPTs to get them up and running again.
Many of the Cleansalls had lids without surrounds, so when the lid was lifted, the surrounding ground collapsed in, and then the lid would not go back on properly and/or left a trip hazard.

Other works included pipe installations, trashrack replacement, supply and installation of new lids for all the CL375 devices, creek cleanouts and decommissioning of a very poorly located GPT installed by a developer in a residential backyard.

Council is now well progressed with completion of the rectification list that was one of the key outcomes from the audit.