City of Sydney – 20 x Stormwater Harvesting Projects Audit, Rectification Optimisation & Operation
Following engagement for the Operation and Maintenance of 20 x stormwater harvesting plants for the City of Sydney, Optimal Stormwater provided a Infrastructure Operating Plan to bring all of these 20 plants to operational status.
The overall operational status was less than 50% and was increased to 95% in less than three months. Today the City of Sydney is enjoying 100% operational status and looking forward to further optimisation to the improve sustainability of each scheme.
Optimal has provided all the skills including civil, process, electrical and automation engineers, electricians, service technicians and mechanical fitters for the optimisation operation and maintenance.
The 20 x projects currently under contract include
- Alexandria Oval, Alexandria
- Barcom Reserve, Darlinghurst
- Beare Park, Elizabeth Bay
- Corning Park, Waterloo
- Crown Park, Waterloo
- Epsom Road Depot, Zetland
- Harmony Park, Surry Hills
- Lillian Fowler Reserve, Newtown
- Mary O’Brien Park, Zetland
- Nuffield Park, Zetland
- Paddington Reservoir Gardens, Paddington
- Peace Park, Chippendale
- Pirrama Park, Pyrmont
- Prince Alfred Park, Surry Hills
- Redfern Park & Oval, Redfern
- Solander Park, Erskineville
- St James Park, Glebe
- Sydney Park, St Peters
- Turruwul Park, Rosebery
- Waterloo Oval, Waterloo